King Street West/ Chestergate
303B/C King St West/Chestergate
Progress made during w/c 20.08.2018
· Temporary cessation of imported fill to carriageway construction on new horseshoe and concrete protection to existing services within the former footway, until United Utilities diversion is completed. Southern footway closure on Chestergate in place between Kingston St and King St West to enable these works
· Footway widening works on Chestergate (East of King St West junction) Northern footway are continuing under a lane closure and banned left turn onto Chestergate from King St West southbound traffic). Pedestrians managed t through site and onto southern footway of Chestergate (east of King St West junction)
· Splitter island construction and pipe insertion on Chestergate (east of King St West junction)
· Installation of copings to boundary wall to new carpark
· Installation of path edgings associated groundworks
· Erection of masonry buttresses to inside of Nursery wall (playground elevation)
Look ahead for w/c 27.08.2018
· Recommencement of works to the horseshoe area of Chestergate/King St West to install ENWL and Vodafone ducting within site extent. Concrete protection to existing services within the former footway and subsequent filling of carriageway widening to sub-base level. Southern footway closure on Chestergate in place between Kingston St and King St West to enable these works
· Footway widening works on Chestergate (East of King St West junction) Northern footway are continuing under a lane closure and banned left turn onto Chestergate from King St West southbound traffic). Pedestrians managed though site and onto Southern footway of Chestergate (East of King St West junction)
· Splitter island construction and pipe insertion on Chestergate (east of King St West junction)
· Brickwork and copings to all walls in advance of 03/09/2018
· Gate installations in advance
· Car park final surface dressing and road markings
Knightsbridge
Progress made during w/c 20.08.2018
· Northern footway on Great Portwood Street in-situ
· Footway closure to western footway on Knightsbridge and subsequent removal of bus stop on Knightsbridge
· Site clearance and drainage installation to western footway on Knightsbridge
Look ahead for w/c 27.08.2018
· Northern footway on Great Portwood Street in-situ
· Footway closure to Western footway on Knightsbridge and subsequent removal of bus stop on Knightsbridge
· Site clearance and drainage installation to western footway on Knightsbridge
· Additional strengthening works to Park Bridge wing wall
M60 Junction 1 (Hollywood Way)
Progress made during w/c 20.08.2018
· Drainage installations to junction of Hollywood Way/Brinksway
· Splitter island construction on Brinksway
· Street lighting installations on the junction of both Hollywood Way/Brinksway and Yew St Hollywood Way
Look ahead for w/c 27.08.2018
· Ducting installation to Hollywood Way
· Centre island and central reserve construction on Hollywood Way
· Street lighting installations on the junction of both Hollywood Way/Brinksway and Yew St Hollywood Way
Travis Brow Link Road
Progress made during w/c 20.08.2018
· Drainage works continuing on Heaton Lane after stats findings. Backfill and dig and connections.
· Ground anchors continued. Platforms being formed for future anchoring works.
· Backfill and drainage system in place behind L shaped wall. Front stoning up taking place.
· Wellington Road kerbs and footways work
· Earthworks on front of embankment
Look ahead for w/c 27.08.2018
· Platform works to continue for future anchor works.
· Ground anchors to continue.
· Backfill of L shaped wall to continue
· Pile trimming to resume.
· Wellington road footway and kerbing works to continue.