King Street West/ Chestergate
Progress made during w/c 30.07.2018
· Temporary cessation of imported fill to carriageway construction on new horseshoe and concrete protection to existing services within the former footway, until United Utilities diversion is completed. Southern footway closure on Chestergate in place between Kingston St and King St West to enable these works.
· Footway widening works on Chestergate (East of King St West junction) Northern footway are continuing under a lane closure and banned left turn onto Chestergate from King St West southbound traffic). Pedestrians are to managed access through site and onto Southern footway of Chestergate (East of King St West junction).
· Enabling works for fencing installation
Look ahead for w/c 06.08.2018
· Temporary cessation of imported fill to carriageway construction on new horseshoe and concrete protection to existing services within the former footway, until United Utilities diversion is completed. Southern footway closure on Chestergate in place between Kingston St and King St West to enable these works.
· Footway widening works on Chestergate (East of King St West junction) Northern footway are continuing under a lane closure and banned left turn onto Chestergate from King St West southbound traffic. Pedestrian access maintained through site and onto southern footway of Chestergate (East of King St West junction).
· Lining works to carriageway
· Cleaning of brickwork
· Terracotta installation and plinth installation to continue
· Enabling works for car park to commence
Knightsbridge
Progress made during w/c 30.07.2018
· Site clearance to Great Portwood St, Southern footway under a night closures
· Kerbing and ducting infrastructure to Great Portwood St, Southern footway under a night closures
· Ducting infrastructure to Great Portwood St, southern footway under a night closures
· Paving to Great Portwood St, southern footway under a night closures
· Footway closure to eastern footway on Knightsbridge and northern footway on Great Portwood Street
· Kerbing to new highway widening on Knightsbridge eastern extent
· Footway paving and edge retention system to Knightsbridge, eastern footway
Look ahead for w/c 06.08.2018
· Site clearance to Great Portwood St, Southern footway under a night closures
· Kerbing and ducting infrastructure to Great Portwood St, southern footway under a night closures
· Substantial completion of paving to Great Portwood St, Southern footway under a night closures
· Footway closure to Eastern footway on Knightsbridge and Northern footway on Great Portwood Street
· Kerbing to new highway widening on Knightsbridge eastern extent
· Footway paving and edge retention system to Knightsbridge, Eastern footway
M60 Junction 1 (Hollywood Way)
Progress made during w/c 30.07.2018
· Low level path construction nearing completion
· Street lighting complete
· Kerbing works to Brinksway junction
· Footway ducting
· Kerbing to Hollywood Way
· CBR testing
· Carriageway formation at Hollywood Way
Look ahead for w/c 06.08.2018
· Low level footpath construction to complete
· Street lighting connections to be made and feeder pillar upgrade
· Kerb installation to Brinksway
· Kerbing to Hollywood Way
Note: From 6pm Saturday 11th to 10am Sunday 12th August 2018 there is a requirement for us to close the Hollywood Way approach to M60 Junction 1 to all vehicles from its junction with Yew Street. The Hollywood Way exit from M60 Junction 1 will be maintained. The signed diversion route will be via A560 Brinksway / Chestergate (eastbound), A560 King Street West (northbound) and A5145 Travis Brow (westbound).
Travis Brow Link Road
Progress made during w/c 30.07.2018
· Site set up on with welfare facilities and traffic management. Lane 1 on Wellington Road North, southbound is closed for pedestrian diversion.
· 4no trial holes in footway outside Kingsgate have been dug finding numerous services in each. Dig out for lamp column relocation undertaken on Thursday 2nd and electricity cable had been struck. ENWL to fix.
· Travis Brow top soil strip, reduced dig and disposal of embankments continuing.
· Travis Brow, RC Pile cropping taking place all week and marking out for future crops.
Look ahead for w/c 06.08.2018
· Heaton Lane roundabout drainage works to commence, part of roundabout to be closed for drainage connection works.
· Footway and paving works to be carried out on Wellington Road North
· Travis Brow, excavation and disposal of embankments off site, reduced level dig continues.
· Travis Brow, RC Pile cropping and clearance works to continue.
· Excavation for foundation for L shape retaining wall units and installation of units.