St Mary’s Way
Progress made during w/c 09.04.2018
St Mary’s Way/ Hall Street Junction
· Completion of installation of the new traffic light and street lighting infrastructure
· Continuation of landscaping, site clearance and drainage and kerbing installation
· Completion of westbound lane narrowing on Spring Gardens, from its junction with St Mary’s Way to the bus layby, by 13/04/2018
St Mary’s Way/ Newbridge Lane Junction
· Continuation of landscaping with the installation of trees and soft landscaping
· Continuation of the footway surfacing has commenced on the 102 scheme and will continue to its conclusion over the coming weeks, following old lighting equipment removal. Note: the shared use footway up St Mary’s Way will not be surfaced until Hall Street works are completed.
Look ahead for w/c 16.04.2018
St Mary’s Way/ Hall Street Junction
· Continuation of landscaping to all areas on scheme
· Commencement of new traffic signal installation
· Completion of footway up the hill on St Mary’s Way to base course only
· From Monday 16.04/18 for approximately 2 weeks there is a requirement to close St Mary’s Way (between Portwood Roundabout and Hall Street) and Spring Gardens (between Waterloo Road and St Mary’s Way) overnight, 8pm to 5.30am Monday to Friday to allow surfacing works to progress.
St Mary’s Way/ Newbridge Lane Junction
· As above
Note: · For one week during week commencing 30/04/18, temporary traffic signals will be in operation at the St Mary’s Way/ Hall Street junction while TfGM commission the new permanent signals. We will work with TfGM to time the temporary signals to best manage flows during this time.
M60 Junction 1 (Hollywood Way)
Progress made during w/c 09.04.2018:
- Rebar construction for stem in walls 7, 8 and 13
- Rebar bar to base wall 5
- Stem of walls and 13 cast
- Excavation and ground improvement to walls 3 and 4
- Waterproofing of Reinforced concrete bases on walls 5 and 13
- Re-covering of exposed BT ducts (see item below)
Look ahead for w/c 16.04.2018:
- Stem construction for walls 7 and 8
- Base construction for wall 3
- Steel fixing to walls 3 and 5
- Ongoing excavation and ground improvement
- Slewing of BT cables on Yew St (delay due to BT not supervising works, planning for Tue 17th)
A555 Drainage Update
Progress made during w/c 09.04.2018:
- Hydrobrake base and first ring installed
- First foamed concrete pour complete (80m3)
Look ahead for w/c 16.04.2018:
- Strip out bottom temp works frame
- Construct second hydrobrake ring
- Commence with weir wall construction (inside hydrobrake chamber)