Chestergate/ King Street West
Progress made during w/c 16.07.2018:
· Brickwork installation ongoing and to complete
· Wood St surfaced
· Car park to binder level
· Extension of service pits
· Kerbing and footway expansion to Chestergate
Look ahead for w/c 23.07.2018:
· Lining to Wood St
· Final works to Lundy’s yard area and cleaning
· Car park works to continue
· Landscaping to boundary area
· Service duct installation
· Widening of existing trenches
Knightsbridge
Progress made during w/c 16.07.2018:
· Street lighting and traffic light infrastructure installation
· Plinth detail being installed
· Footway construction ongoing
· Kerbing to widened highway
Look ahead for w/c 23.07.2018:
· Street lighting and traffic light infrastructure installation
· Footway construction to continue
· Duct crossings in carriageway of junction
· Plinth construction to continue
· Kerbing to widened highway
M60 Junction 1 (Hollywood Way)
Progress made during w/c 16.07.2018:
· Low level path construction ongoing
· Kerbing works to Brinksway junction
· Footway ducting
· Drainage installation ongoing
Look ahead for w/c 23.07.2018:
· Low level footpath construction to continue
· Street lighting works to complete
· Drainage works to continue
· Kerb installation to Brinksway
· Setting out of Hollywood Way junction
Travis Brow Link Road
Progress made during w/c 16.07.2018:
· Travis Brow top soil strip and disposal of embankments continuing.
- Statutory services diversions to A6 Wellington road North are 95% complete. Now rescheduled to be completed by 27th July.
- Retaining wall RC vertical pile installation progressing with 95 % of piles installed to date, levels 1-3 are complete.
- Temporary works: final piling mat platform 4 completed and checked
- Wellington Road North Street lighting diversions continuing.
Look ahead for w/c 23.07.2018:
- Travis Brow, excavation and disposal of embankments, reduced level dig continues
- Statutory services diversions to A6 Wellington Road North (water/ electricity) continuing.
- Retaining wall piling to Travis Brow embankment levels 4 continuing (scheduled to complete early in the week.
- Demob of drilling rig and associated plant.
- Highway works to wellington Road North delayed due to ongoing service diversions, now scheduled to begin week commencing 30th July 2018.