King St West/Chestergate
Progress made during w/c 02.07.2018
· Enabling works on Cooke Street for service transfer from DMex building to EcoBuild
· Excavation for carriageway widening and kerb chase on horseshoe around existing services in former footway. Southern footway closure on Chestergate in place between Kingston St and King St West to enable these work
· Installing ducting for service providers
· Brickwork installation to Wood Street nursery wall
· Scaffold removal
Look ahead for w/c 09.07.2018
· Completion of G. Cox and subcontractor enabling works on Cooke Street for service transfer from DMex building to EcoBuild
· Commencement of imported fill to carriageway construction on new horseshoe with concrete protection to existing services within the former footway. Southern footway closure on Chestergate in place between Kingston St and King St West to enable these works.
· Installing ducting for service providers
· Brickwork installation to Wood Street nursery wall
· Car park works to commence
Knightsbridge
Progress made during w/c 02.07.2018
· Street lighting and traffic light infrastructure installation on Warren Street and Knightsbridge footways
· Site clearance, kerbing and footway paving to Warren Street, north footway under a lane narrowing
· footway closure to eastern footway on Knightsbridge and northern footway on Great Portwood Street
· kerbing to new highway widening on Knightsbridge eastern extent
· drainage installation and carriageway sub-base and base construction to highway widening extent to the east of Knightsbridge
Look ahead for w/c 09.07.2018
· Street lighting and traffic light infrastructure installation on Warren Street and Knightsbridge footways
· Site clearance, kerbing and footway paving to Warren Street, north footway under a lane narrowing
· footway closure to eastern footway on Knightsbridge and northern footway on Great Portwood Street
· kerbing to new highway widening on Knightsbridge eastern extent
· drainage installation and carriageway tarmacadam base construction to highway widening extent to the east of Knightsbridge
M60 Junction 1 (Hollywood Way)
Progress made during w/c 02.07.2018:
· All concrete works complete
· All scaffold removed
· Waterproofing complete
· Low level path construction ongoing
· Street light installation
· Footway duct crossing at Brinksway junction on nights
· Relocation of traffic lights at Brinksway junction complete
· Drainage works to commence
Look ahead for w/c 09.07.2018:
· Low level footpath construction to continue
· Footway duct crossings to Brinksway junction on nights
· Island ducting to Brinksway junction on nights
· Drainage works to continue
Travis Brow Link Road
Progress made during w/c 02.07.2018
· Travis Brow site clearance, tree removal, top soil strip and disposal of embankments continuing
· Drainage/ ground investigation surveys complete
· Statutory services diversions to Travis Brow and A6 90% complete
· Redundant Rail Tunnel demolished and backfilled
· New sewer connection to A6 nearing completion on nights
· Network Rail repairs to Viaduct Arch and monitoring system complete
· Retaining wall piling to Travis Brow progressing
· Soil Nailing site loading tests complete
Look ahead for w/c 09.07.2018
· Travis Brow, disposal of embankments continuing
· Statutory services diversions to A6 (water/ electricity) scheduled to be completed by 13th July 2018
· New sewer connection to A6 day time working Monday through Wednesday 11/07/2018
· Retaining wall piling to Travis Brow embankment continuing