Weekly Update on Key Town Centre Access Plan Projects
Below is an update on progress last and week and look ahead to next week for the following key TCAP Projects:
- King Street West/ Chestergate
- Knightsbridge
- M60 Junction 1 (Hollywood Way)
- Travis Brow Link Road
For details of Traffic Management in place wc 25.06.18 across all TCAP schemes, please see https://www.stockport.gov.uk/town-centre-access-plan/traffic-management-tcap )
King Street West/Chestergate
Progress made during w/c 25.06.2018:
- Brickwork installation Wood Street Nursery Wall to continue
- Wood St laid to binder level
- Hardman Street surfaced
- Completion of BT chamber re-builds on junction of Chestergate/King St West
- Enabling works on Cooke Street for service transfer from DMex building to EcoBuild
- Completion of Site compound establishment commencing for highways element of scheme
- Excavation for carriageway widening and kerb chase on horseshoe.
Look ahead for w/c 02.07.2018:
- Brickwork installation Wood Street Nursery Wall to continue
- Car park works
- Surface course to Wood Street
- Footway surfacing to Gough Street
- Enabling works on Cooke Street for service transfer from DMex building to EcoBuild
- Backifilling of excavation for carriageway widening and kerb chase on horseshoe followed by commencement of kerbing
Knightsbridge
Progress made during w/c 25.06.2018
- New electricity service installation for scheme
- Street lighting and traffic light infrastructure installation on Warren Street and Knightsbridge footways
- Site clearance, kerbing and footway paving to Warren Street, North footway under a lane narrowing
- Kerbing to new highway widening on Knightsbridge eastern extent
- Drainage installation to highway widening extent to the East of Knightsbridge
- Carriageway sub-base and base construction to highway widening extent to the East of Knightsbridge
- Closure of Knightsbridge, between Lancashire Hill and Great Portwood St, from 27.06.2018 for four nights (7pm to 5am) for the installation of drainage pipes within the existing carriageway.
Look ahead for w/c 02.07.2018
- Street lighting and traffic light infrastructure installation on Warren Street and Knightsbridge footways
- Site clearance, kerbing and footway paving to Warren Street, North footway under a lane narrowing
- Kerbing to new highway widening on Knightsbridge eastern extent
- Drainage installation to highway widening extent to the East of Knightsbridge
- Carriageway sub-base and base construction to highway widening extent to the East of Knightsbridge
M60 Junction 1 (Hollywood Way)
Progress made during w/c 25.06.2018:
- Final concrete pour complete
- Scaffold being removed
- Waterproofing
- Carriageway/footway duct crossing at Brinksway junction on nights
- Transport for Greater Manchester Relocation of permanent traffic lights to allow works to progress
- Setting out
- Drainage works set out
- Low level path construction
Look ahead for w/c 02.07.2018:
- Backfilling to wall
- Detail design to continue
- Low level footpath construction
- Site tidy and clean
- Setting out
- Carriageway/footway duct crossings to Brinksway junction on nights
- Drainage works to continue
Note: Motorists will not see significant activity taking place during the day at Hollywood Way, as most (and all disruptive) works are taking place overnight.
Travis Brow Link Road
Progress made during w/c 25.06.2018
- Contiguous bored pile wall installation (off highway)
- Soil nail slope stabilisation installation (off highway)
- Utility diversions on A6 (single lane operating in both directions)
Progress made during w/c 02.07.2018
- Contiguous bored pile wall installation (off highway)
- Soil nail slope stabilisation installation (off highway)
- Utility diversions on A6 (footpath restrictions on west footpath)
- w/c 02.07.18: Combined sewer connection into an existing manhole in the A6 carriageway – overnight single file traffic signal control 7pm to 6am from Tuesday to Friday inclusive.
- Following week daytime traffic restrictions but single lane in both directions (as per existing).