St Mary’s Way
Progress made during w/c 11.06.2018
· Continuation of signage installation to all areas
· Completion of pedestrian guard rail on St Mary’s Way (uphill) for five days (nearside lane narrowing only)
Look ahead for w/c 18.06.2018
· Continuation of signage installation to all areas
· Installation of pedestrian guard rail on St Mary’s Way (uphill) (nearside lane narrowing only)
King Street West/ Chestergate
Progress made during w/c 11.06.2018
· BT chamber re-builds on junction of Chestergate/King St West. Pedestrian diversion in place via Heaton Lane roundabout pedestrian crossing.
· Enabling works on Cooke Street for service transfer from DMex building to EcoBuild
· Site compound establishment commencing for highways element of scheme
· Site clearance undertaken for removal of vegetation on horseshoe
· Trial holes to be undertaken off highway, on former site of public house to review extent of excavation required
· Brickwork installation on Wood Street nursery wall
· Kerbing works to Wood St exit ongoing
· Footway works to internal area commenced
· Brickwork sample approved by Paul Hartley on 08/06/2018. Plinth being manufactured
Look ahead for w/c 18.06.2018
· BT chamber re-builds on junction of Chestergate/King St West. Pedestrian diversion in place via Heaton Lane roundabout pedestrian crossing.
· Enabling works on Cooke Street for service transfer from DMex building to EcoBuild
· Trial holes continue to be undertaken off highway, on former site of public house to review extent of excavation required
· Brickwork installation on Wood Street nursery wall
· Car park works
Knightsbridge
Progress made during w/c 11.06.2018
· Installation of new electricity connection
· Street lighting and traffic signal infrastructure installation on Warren Street and Knightsbridge footways
· Site clearance, kerbing and footway paving to Warren Street, North footway under a lane narrowing
· Kerbing to new highway widening on Knightsbridge eastern extent
· Drainage installation to highway widening extent to the East of Knightsbridge
Look ahead for w/c 18.06.2018
· Installation of new electricity connection
· Street lighting and traffic signal infrastructure installation on Warren Street and Knightsbridge footways
· Site clearance, kerbing and footway paving to Warren Street, North footway under a lane narrowing
· Kerbing to new highway widening on Knightsbridge eastern extent
· Continuation of drainage installation to highway widening extent to the East of Knightsbridge
M60 Junction 1 Hollywood Way
Progress made during w/c 11.06.2018:
· Stringcourse construction ongoing
· Import of material
· Backfill behind wall ongoing and nearing completion
· Cantilever slab complete (base)
· Carriageway duct crossing at Brinksway junction appx. 80% complete
Look ahead for w/c 18.06.2018:
· Stringcourse and cantilever slab construction
· Import of material and backfilling behind wall
· Carriageway duct crossings to Brinksway junction on nights
· UTC relocation of signals into barrels (nights of 19th and 20th)
A555 Drainage Repair
Progress made during w/c 11.06.2018:
· Resurfacing works to be completed and A555 westbound between the A34 and B5358 Wilmslow Road reopened on 17th June 2018.
Look ahead for w/c 18.06.2018:
· Drainage repairs complete, no further works required.
· A555 eastbound from A34 to B5358 Wilmslow Road to be closed from 18.06.18 for 6 week as part of main A6MARR project. Further information provided on the SEMMMS website.