Progress made during w/c 16.04.2018:
• Removal of existing refuge island and construction of new island
• Footway construction
• Topsoil added to verges
• Resurfacing works
• Installation of traffic lights and street lights
Look ahead for w/c 23.04.2018:
* Topsoil added to verges
* Footway construction
* Surfacing works
* Installation of traffic lights
* From Monday 16.04.18 for approximately 2 weeks, St Mary’s Way (between Portwood Roundabout and Hall Street) and Spring Gardens (between Waterloo Road and St Mary’s Way) are closed overnight, week nights 8pm to 5.30am to allow surfacing works to progress.
Note:
• For one week during week commencing 30/04/18 temporary traffic signals will be in operation at the St Mary’s Way/ Hall Street junction while TfGM commission the new permanent signals. We will work with TfGM to time the temporary signals to best manage flows during this time.
M60 Junction 1 (Hollywood Way)
Progress made during w/c 16.04.2018:
• Rebar construction ongoing throughout wall
• Concrete works to - Stem wall 7, base wall 3, stringcourse wall 12 and 13
• Excavation and ground improvement to walls 9, 10 and 11
• Waterproofing of reinforced concrete bases and stems
• Back of wall drainage installation
• Re-covering of exposed BT ducts
Look ahead for w/c 23.04.2018:
• Reinforced concrete works
• Steel fixing
• Ongoing excavation and ground improvement
• Waterproofing
A555 Drainage Repairs
Progress made during w/c 16.04.2018:
• Installation of new drainage infrastructure continuing
• Second foamed concrete pour (80m3) complete
• Commenced with construction of weir wall for hydrobrake
Look ahead for w/c 23.04.2018:
• Pipework connections made between access chambers
• New outfall chamber construction
• Continue to construct weir wall in hydrobrake chamber
• Preparation for third foamed concrete pour
Note: The below photograph was taken this week showing the removal of the bottom frame for the excavation.