St Mary’s Way
Progress made during w/c 02.04.2018
St Mary’s Way/ Hall Street junction
· Continuation of installation of drainage, kerbing and new traffic light and street lighting infrastructure
· Continuation of landscaping to all areas on scheme
· Continuation of site clearance works
· Removal of lane closure on St Mary’s Way northbound approach to junction by 06.04.18
St Mary’s Way/ Newbridge Lane junction
· Continuation of landscaping with the installation of trees and soft landscaping
· Continuation of the footway surfacing
Look ahead for w/c 09.04.2018
St Mary’s Way/ Hall Street junction
· Continuation of installation of drainage, kerbing and new traffic light and street lighting infrastructure
· Continuation of landscaping to all areas on scheme
· Continuation of site clearance works
· Removal of westbound lane narrowing on Spring Gardens, from its junction with St Mary’s Way to the bus layby, by 13/04/2018
St Mary’s Way/ Newbridge Lane junction
· Continuation of landscaping with the installation of trees and soft landscaping
· Continuation of the footway surfacing (to be completed by 04.05.18)
Note: · From Monday 16.04/18 for approximately 2 weeks there is a requirement to close St Mary’s Way (between Portwood Roundabout and Hall Street) and Spring Gardens (between Waterloo Road and St Mary’s Way) overnight, 8pm to 5.30am Monday to Friday to allow surfacing works to progress. Communications associated with the closures will include: letter to adjacent properties, website update, on site signage and social media.
· For one week during week commencing 30/04/18, temporary traffic signals will be in operation at the St Mary’s Way/ Hall Street junction while TfGM commission the new permanent signals. We will work with TfGM to time the temporary signals to best manage flows during this time.
M60 Junction 1 (Hollywood Way)
Progress made during w/c 02.04.2018:
· Rebar construction for stem in walls 6, 7 and 8
· Stem in wall 13 cast
· Excavation and ground improvement to wall 4 and 5
· Waterproofing of RC bases in walls 5,6,7, 8, 12 and 13
Look ahead for w/c 09.04.2018:
· Stem construction for walls 5, 6 and 12
· Base construction for wall 4
· Steel fixing to walls 4 and 5
· Ongoing excavation and ground improvement
· Slewing of BT cables on Yew St
A555 Drainage Repair
Progress made during w/c 02.04.2018:
- base for hydrobrake complete
- installation of hydrobrake chamber started
Look ahead for w/c 09.04.2018:
- continuation of hydrobrake chamber installation
- installation of associated pipework
- preparation for first foamed concrete pour
Note: The works are currently still on schedule to be completed within the advertised 17 week period.