St Mary’s Way
Progress made during w/c 26.03.2018
St Mary’s Way/ Hall Street Junction
· Continuation of installation of drainage and traffic light and street lighting infrastructure
· Continuation of landscaping to all areas on scheme
· Completion of site clearance works to the Western footways and channel lines on St Mary’s Way, to the North of the junction and to central islands on Hall Street/Spring Gardens
· Completion of installation of kerbing to Western channels on St Mary’s Way, to the North of the junction and to central islands on Hall Street/Spring Gardens
· Completion of single lane northbound running on St Mary’s Way, to the north of the junction on 27.03.18
· Completion of single lane eastbound running on Spring Gardens by 29.03.18
St Mary’s Way/ Newbridge Lane Junction
· Continuation of footway surfacing and landscaping planting
Look ahead for w/c 02.04.2018
St Mary’s Way/ Hall Street Junction
· Continuation of installation of kerbing, drainage and traffic light and street lighting infrastructure
· Continuation of landscaping to all areas on scheme
· Continuation of site clearance works
· Lane closure on northbound approach to St Mary’s Way/ Hall Street junction 3 – 6.04.18
St Mary’s Way/ Newbridge Lane Junction
· Continuation of footway surfacing and landscaping planting
Note:
· The St Mary’s Way works are now nearing their completion which has allowed us to remove much of the traffic management in place on St Mary’s Way. All but essential traffic management will be removed over the Easter weekend, with the above noted lane closure on the St Mary’s Way northbound approach to the Hall Street junction in place from 3 – 6.04.18.
· Resurfacing works requiring road closures will be carried out overnight over the coming weeks. Updates will be provided once dates are confirmed.
M60 Junction 1 (Hollywood Way)
Progress made during w/c 26.03.2018:
· Rebar construction for stem in walls 6, 7 and 8
· Base walls 12 and 13 complete
· Excavation and ground improvement to walls 4 and 5
· Waterproofing of reinforced concrete bases in walls 6, 7 and 8
Look ahead for w/c 02.04.2018:
· Stem construction and steel fixing to walls for walls 12 and 13
· Steel fixing to walls 4 and 5
· Ongoing excavation and ground improvement
· Lane 1 closure on Yew Street in place from 2.01.18 for a period of c. 6 months
A555 Drainage Repair
Progress made during w/c 26.03.2018:
· Temporary works complete
· Dig to formation level complete
· Blinding concrete poured at formation level ready for new infrastructure
Look ahead for w/c 02.04.2018:
· Falsework construction for Hydrobrake base
· Steel fixing for base slab
· Pour concrete base slab