St Mary’s Way
Progress made during w/c 19.03.2018
St Mary’s Way/ Hall Street Junction
· Continuation of installation of drainage and new traffic light and street lighting infrastructure
· Continuation of footway construction, surfacing work and landscaping
· Site clearance and kerb installation
St Mary’s Way/ Newbridge Lane Junction
· Continuation of footway surfacing and landscaping planting
· Highway widening for new left turn off Knightsbridge
Look ahead for w/c 26.03.2018
St Mary’s Way/ Hall Street Junction
· Continuation of installation of drainage and new traffic light and street lighting infrastructure
· Continuation of footway construction, surfacing work and landscaping
· Continuation site clearance and kerb installation
· St Mary’s Way single lane northbound running from 12/03 for approximately 4 weeks
· Spring Gardens eastbound single lane running from 12/03 for approximately 3 weeks
St Mary’s Way/ Newbridge Lane Junction
· Continuation of footway surfacing and landscaping planting
· Highway widening for new left turn off Knightsbridge
Note: this week, TfGM’s Urban Traffic Control carried out a review of the traffic signal timings at the Hall Street/ St Mary’s Way junction in light of changes to traffic flows caused by the TM currently in place to best manage traffic flows on St Mary’s Way.
M60 Junction 1 (Hollywood Way)
Progress made during w/c 19.03.2018:
· Hydro-demolition works complete
· Scaffold removed
· Bases for walls 6, 7 and 8 complete
· Excavation working towards subway ongoing
Look ahead for w/c 26.03.2018:
· Bases for walls 6, 7 and 8 complete
· Steel fixing
· Ongoing excavation
· Lane 1 closure on Yew Street in place from 2.01.18 for a period of c. 6 months
Note:
· This week, TfGM’s Urban Traffic Control carried out a review of the traffic signal timings at the M60 Junction 1 to ensure that traffic flows are best managed in light of the lane 1 closure on Yew Street.
· No complaints about traffic management have been received this week since the traffic management has been removed from the M60 junction 1 roundabout.
A555 Drainage Repair
Progress made during w/c 19.03.2018:
· Second frame installation complete
· Import and place stone to support additional temporary works
· Additional temporary works commenced. Concrete pour due today (Friday)
· Manhole rings delivered to site
Look ahead for w/c 26.03.2018:
· Remove imported stone from additional temporary works
· Continue dig to formation level (approx. 1m additional)
· Pour concrete base at formation level ready for new infrastructure
· Procure vertical ground penetrating radar survey for retaining walls and abutment